Boggabri Coal - Facilities Upgrade

IDEMITSU BOGGABRI COAL,
BOGGABRI NSW
SITE FACILITIES UPGRADE

This project comprised of 5 stages of work, with the Stage 1 being to procure, supply and complete the
onsite installation of a new 27m x 12m modular office complex. Civil and concrete works were completed by our Stripes Engineering team. Ancilliary works completed in Stage 1 included the decommissioning of old offices and earthworks required for the construction of a temporary carpark.


Stage 2 involved the relocation and refurbishment of demountable office buildings onsite.


Stage 3 involved the fabrication of structural steelwork and site installation of the steel frames and
260m² of timber decking including roofing and guttering.


Stages 4 & 5 comprised of the civil and concreting works required to complete the establishment of permanent light and heavy vehicle carparks including the trenching for cables and installation of
footings for light poles, installation of concrete ramps and paths and the fabrication and site installation of a screen wall and BBQ Area to compliment the site facilities upgrade.


Practical completion of the project was achieved on time and within budget.

Duration: 5 Months