Project Overview
Locally Fabricated Structural Steel Delivery
Stripes delivered the structural steel package for North Constructions at the new render plant within Bindaree Food Group’s Inverell beef-processing facility.
The approximately 1,400-square-metre rendering building incorporated precast and structural steel across the raw-material, cooking and meal-processing areas. Stripes completed shop detailing, fabrication, transport, erection, coordination and certification for the steel package.
The project demonstrated the value of integrated regional capability by connecting fabrication in the Stripes Gunnedah workshop with coordinated delivery and installation on site.
Project Scope
- Structural steel fabrication
- Workshop quality assurance
- Transport and delivery to site
- Structural steel erection
- Installation coordination within an operating facility
- Approximately 1,400 square metres of main-frame structure